When Meta selected a site in Louisiana for its largest data center to date, it signed a deal with Entergy to power the site ...
If the Public Service Commission approves the plan, Entergy will have the greenlight to build three new gas plants to power ...
The Louisiana Public Service Commission, or LPSC, has approved a landmark agreement that paves the way for Entergy Louisiana ...
Fast-tracking a vote that was originally expected to happen two months from now, state utility regulators plan to decide ...
Meta’s data center will need about three times the amount of electricity that New Orleans uses in a year and increase Entergy ...
The Louisiana Public Service Commission (LPSC) has approved an agreement that enables Entergy Louisiana to proceed with ...
22hon MSN
Entergy receives regulatory approval for investments to support Meta's Louisiana data center
Entergy's Louisiana unit received the state's regulatory approval to move forward with infrastructure investments tied to ...
The Louisiana Public Service Commission (LPSC) has given the go-ahead for the installation of three natural gas turbines set to power Meta’s planned 2GW data center in Richland Parish, Louisiana.
Louisianas Public Service Commission approved Entergys proposal to build three combined-cycle gas turbines and supporting transmission infrastructure to power Metas $10 billion AI data center in ...
The Louisiana Public Service Commission voted 4-1 to approve Entergy’s plan to build three natural gas power plants for Meta’s $800M data center in Richland Parish ...
The Louisiana Public Service Commission (PSC) will outline its after-action findings in Baton Rouge following the outage, ...
Louisiana utility regulators on Wednesday approved Entergy Louisiana’s plan to build new natural gas plants and transmission ...